The incremental launching method is one of the highly mechanised erection methods used in bridge construction. The method consists of manufacturing the superstructure of a bridge by sections in a prefabrication area behind one of the abutments; each new unit is concreted directly against the preceding one and after it has hardened the resultant structure is moved forward by the length of one unit.


Incremental Launching Method scheme

During the construction stage the superstructure is centrally prestressed, to limit the tensile stresses produced by the bending moments. The skilful use of prestressing is the most important of this construction sequence.


Sudirman Flyover, Jakarta, Indonesia

Sudirman Flyover, Jakarta, Indonesia
VSL Scope of Work: Design and construction of superstructure including the preparation of casting yard, placing the reinforcement, casting the segments, supply pot bearing, post-tensioning, design and supply of launching nose and launching 2 nos of parallel cell box girders with skew angle of 30 degrees. The flyover has a total length of 165m with main span of 37m. Record in 2000 as the first bridge launched incrementally in Indonesia

Tubun Flyover, Jakarta, Indonesia
Incremental launching type of construction which having total length 255m and composed of 40, 55, 65, 55 and 40m span.
VSL scope of work: Design of casting yard, supply and install of post-tensioning, design and operate the launching system and supply pot bearing.
Registerd by MURI (Indonesian Records Museum) in 2000 as the largest main span bridge launched incrementally in Indonesia

Bridge Erection - Ereksi Jembatan

Bridge Erectione-mail: vslin@vslin.com - phone: (+6221) 5700786



Precast segmental balanced cantilever erection with overhead launching gantry
Pasupati Project, Bandung, Indonesia















Method drawing for precast segmental erection with launching gantry and temporary supports equipped with adjustment device for pier segment and one downstream segment alignment. Pasupati Project, Bandung, Indonesia
















































Throughout the world, VSL's record of experience in bridge construction includes literally hundreds of different types of bridges: balanced cantilever, cable-stayed, suspension bridge, incremental launching, box jacking, precast segmental and cast in situ.

These works are carried out in accordance with strict procedures incorporate systematic quality assurance. In many cases, our expert team will also undertake the project management.


Cast in situ balanced cantilever bridge with form traveler
Muba Bridge, Indonesia

VSL is committed to offering clients a "best for project" service. Arrangements between main contractor and VSL as subcontractor for bridge deck construction or even between owner, consultant, main contractor and VSL have proven to be highly successful and mutually beneficial to all parties involved. Bridges are built not by individuals but by a team of various parties. Main objective of such a team shall be to get the best solutions for the final product with financial rewards for team members linked to successful delivery of the entire work.

Precast segment (150t) lifting with overhead launching gantry. Segment feeding by lowbed trailer. Pasupati Project, Bandung, Indonesia



Precast girder lifting with overhead launching gantry.
Toll road project, Jakarta, Indonesia


Our service for bridge erection includes methods statement, construction stages analysis reports, shop drawings, alignment control, equipment supply and operation.


Precast segmental full-span erection with underslung launching gantry, Barelang, Indonesia
Services & Products
Post-tensioning
Ground Anchors
Retained Earth
Repair & Strengthening
Heavy Lifting
Climbform & Slipform
Stay Cables
Bridge Erection
Incremental Launching
Bearing & Joints
Design & Engineering

Archives
Photo, presentation, video, paper, report, etc.


Precasting mould

Inner form

Segments stockyard
Casting Yard, Barelang Project, Indonesia

We have capabilities and experiences in design, supply and operation of launching gantry, form traveler, lifting frame, incremental launching equipment and casting yard for construction of many kinds of bridges.